Hertzog Avenue Restoration Schedule

Roadwork on Hertzog Avenue continues the week of 9/21/2026; westside sidewalks closed with replacement beginning 9/28/2026.

Published Sep 18, 2026, 2:10 PM EDT | Fountain Hill Borough

Restoration of Hertzog Ave Schedule

Roadwork will continue for the week of 9/21/2026 – 9/25/2026

Westside Sidewalks will be closed the week of 9/21/2026 – 9/25/2026, and replacement of the sidewalk will begin on 9/28/2026 and will take approximately 2-3 weeks.

Garbage Pick Up

Garbage trucks will be able to access Hertzog this Monday (9/21/2026).  Please put your garbage out at the regular location.

Mail Delivery

The Contractor is working with the post office to ensure that mail can be delivered regularly.  However, if your service is disrupted, you may pick up your mail at the main location 535 Wood Street in Bethlehem.  To inquire if you have mail for pickup, please call 610-866-0911.